AFTER THE SECOND
COMPETITION LICENSE ROUND
M. O. C. WORKED HARD TO START
THE INVESTMENT OF HALFAYA FIELD
After the
coalition of companies (Petrochina one company of C.
N. P. Ccmpanies., Petronas, and Total) had winning
in the investment of Halfaya field, M. O. C. worked
hard to start the work in it. In order to achieve
that aim M. O. C. did the following activities;-

1.M. O. C.
formed a work team to follow-up the work with winner
coalition of companies. A delegation of that
coalition of companies paid a visit to headquarter
of M. O. C. in 23/Jan/2010.The delegation was from
China National Petroleum company (C. N. P. C.) which
was the head of the coalition. The delegation met
the first Deputy of the D. G.
of M. O. C. and the staff developed of it. After
that ,the delegation visited the head quarter of
Myssan province. The delegation met the two deputy
of Myssan Governor. The first Deputy of the D. G
,A. D. G. . of M. O. C., the manger of corporation
of fields and the head of media of M. O. C.
presented that meeting . The delegation told the
officially meeting ,, our coalition will develop
Halfaya field .We shall raise the level of
production to (535000B/D ) during the next seven
years. We shall buy the product crud oil from it,,.
He asked the local government to support the
coalition and help him in his work. The head of
delegation said,, our company is the 5th
company of arrangement of international oil
companies. It has 39Projectes in different
countries. There are(1500000) personal work for it.
In Iraq we work in development 3fields (Remiala, Al-Ahadib
and Halfaya field),,. Finally he invited the senior
officials of province to visit Waset province and
meet the officials of it and to take a familiarity
of running of work in Al-Ahadib field. Mr. Mohamed
Hessian Ali the first deputy of Myssan Governor
welcomed the guests. He invited the China companies
to work in another projects such as building, health
and sports. He tolled them ,, the security in our
province is good and it is safe. He invited them to
publish this true across the Media. Finally, he
confirmed his supporting to M. O. C. and thanked it
for its efforts to develop the province.
The
delegation visited the location of the field in
25/Jan/2010. He visited a number of drilled wells.
He visited the location of drilling Halfaya8 well
and Halfaya degassing station which was build on
2001. At last, the delegation visited the location
of installing the Amarah power station 180Mega Watt
to know the quantity of pure gas which will supply
to it in the next time.

2.M. O. C.
made a workshop in 24/Jan/2010.M.r Mohamed Shia'a
the Governor of Myssan presented it. The mangers of
main offices of Myssan province presented it, too.
At first, the D. G. talk in it to express the
benefits which the country, province and the company
will earn them from the investment of Halfaya field.
He said,, that contract will raise the level of
production to (535000B/D ) during the next seven
years. It will reduce the level of unemployment in
our province. It will help us to develop the
technical level of our employs by training them in
and out the country according the contract. It will
help us to establish a number of trainings center in
our province,,. After that Mr. Sámi Naji the manger
of corporation of fields, Mr. Amad Ahmed the head of
the work team talked and gave more information about
the same subject. They confirmed that contract is
service contract. Mr. Alia Abed Al- Alnebi the
manger of a accounts of the investment plan
department expressed the financials benefits which
will we earn them from the contract. He said ,,the
contractor pay non-refundable 150000000Milion
Dollars to the Ministry when he signed the contract.
He will spend 5Milion Dollars to train our employs
under the same system. He will spend commissioned
oil refundable in the location of field and
additions commissioned refundable out the location
of field. He will deducted 1Doolar and 40Sinet from
every Barrels of oil which product from that field
to the all partners including the government partner
S. O. C. . The Iraqi government will deduct 35% from
it as the income tax. Finally, the Governor of
Myssan thanked M. O. C. to their effects to develop
production to serve the country and the province .
3. M. o. C.
organized a seminar in the hall oil cultural center
in 26/Feb/2010. Mr. Yahaya Abed Ali the A. D. G. of
M.O.C. , Mr. Amad Ahmed the head of work team, Mr.
Mahdi Laibi the manger of protection department and
a number of senior-officials of M. o. C. presented
it. A number of officials of local government, a
number of Military and security officials, a number
of local elder and a number of tribal leaders
presented it, too . The A. D. G. expressed the
benefits which the country, province and the company
will earn them from the investment of Halfaya field.
Mr. Amad Ahmed and Mr. Mahdi Laibi gave more
information about that subject. At last, the
meeting agreed to give high efforts for successes
the work to serve our country, our province and our
company.
|
M.O.C.EXTENDED TRANSPORTING -PIPES
M.O.Cextended transporting –pipe from
Halfaya de –gassing to Myssan refinery .About this
subject M r. Hammed Abass the senior chief engineer
who was the head of the supervision committee told
us ,, the aim of this project was to transport the
crud oil from Halfaya de –gassing station to the
refinery or Bazrgan terminal ,, .We extended pipe
28 Inch to transport the crud oil to the refinery
and returned it to the Faw -Bazrgan pipe .Ibn Majed
company which implemented the project . The project
included extending and wilding pipe 24 Inch is long
24k .m ,pipe 14 Inch with long 5 K .m . Make guide
pipe with 5 K .m
long .The guide crossed rivers,
paved and unpaved streets .

The big problem which faced the
project was the crossing Tigris river but the
farmers rejected pipe crossing in their fields
.These problems were solved by the D .G directives
and the management of the company efforts
THE FUQA WELL/4 IS PURELY IRAQI WELL
The Fuqa well4 is
purely Iraqi well. Mr. Ali Mairech the D. G. of M.
O.C. said that when he
talked to the reporters of media whom M. O.C. made a
free round to them in Fuqa field in25/Dec/2009.
That round was done to express the true to the world
after Iranian forces had occupied the Fuqa well4.The
D. G. told the reporters,, That well was drilling
in 10/Act/1977. It started it's production in
5/Jan/1979. It stopped on September 1980 when the
Iraqi-Iranian war started. That well is linking
with South Fuqa degassing station,,. The reporters
visited that well which was lied near the
Iraqi-Iranian border. They saw the Iranian forces
out the location of the well, but it was still in
the side of Iraqi border. They visited the locations
of wells Fuqa11,13 and Fuqa14.About those wells
which some media said, ,the Iranian forces occupied
them the D. G. said,, the Fuqa well 11 is productive
well. It is linking with North Fuqa degassing
station.
The Fuqa well13
was drilling on1980.It started it's production
on1980 but it stopped from it when the
Iraqi-Iranian war started. It started it's
production again when that war had stopped
.
. The Fuqa well 14 is one of border wells
but there is no problem with Iran about it's
ownership of it. It is non-production well,,. Mr.
Mohamed Shia"a the Governor of Myssan province and a
number of Military and security officials presented
that round. The Military and security officials told
the reporters,, the Iraqi forces took up their
positions near the border wells to protect them from
any threat. At last, we must say the Iranian forces
moved back that well in 27/Jan/2009. Mr. Ali
Al-Debag the spokes man of Iraqi government said
that when he talked to the reporters in green area
in Baghdad.

|
THE D. G. PAID A VISIT TO A NUMBER
OF
LOCATINS OF OIL
The D. G. paid a
visit to the location of bazrgan field. Mr. Yahya
abed Ali the A. D. G. of M. O. C. accompanied him in
that visit. The D. G. visited the location of
building the two washing tanks (1012 and1013) in the
Bazrgan field to has familiarity on the running of
work and solve the problems which faced it, He
visited the unit of treatment the wet oil which had
built before several months ago

.
He visited the
location of joint Noor3 well with Noor degassing
station ,t00. He listened to explanation which was
formed from Mr. Ahssan Abrahem. Mr. Ahssan
confirmed
the workers of constructions branch will finished
the operation joint before the drilling of the well
will be finished. The D. G .thanked them and he
ordered to solve the problems which faced them in
their work's. Mr. Jamel Shait the manger of
corporation of projects accompanied him in that
visit. The D. G. visited the building of Noor
degassing station and met the workers of it. The D.
G. answered their questions, ordered to solve their
problems, and thanked them for their effects to
serve the company and the country.
|
|
|
DELEGATION FROM TRINIDADAXIS VISTED
HEAD QUARTER OF M .O .C
The delegation from Axis company which
was specialist of drilling the oil wells visted M .O
C .The D.G of this company was the head of the
delegation. The delegation contained M r Chapin the
technical manger of it.
This delegation makes a seminar in the
hall of oil cultural center. He gave us historical
summary about this company, known
us with it's technology tools. The
delegation wanted to know the engineering staff in
M.O.C and take idea about the security case in the
province. The delegation gave us summary about their
performance in America ,Shelly and Nigeria .The
delegation show us a number of video films about the
description of its technical tolls which this
company used them in drilling .A number of the
engineers of corporation fields presented this a
seminar. The engineers discussed different subjects
with delegation about the job, if they were
appropriated to work in our fields ,We will make
contract with them. At last the delegation makes
free tour to the out sites of the fields. The
delegation thanked our company to the better
hospitality. The delegation expressed his a
admiration for the technical level of the workers
for M .O .C and drilling company.
|
THE D .G
PAID A VIST TO THEWORK SITES
The D G paid a vist to Noor de
–gassing station which was nearly built at that
days .The vist was happened on 25 /February / 2009
to solve the problems which faced the work and had
supervision on the running of the work

.The station started the
operation when the D .G got it .The technicians
started the test operation at that time .The flare
fired at that time ,too .the two wells ,Noor 1 and
Noor 2 ,had been opened and the oil started flowing
to the station .The D .G thanked the workers and
said ,,it is large performance .It would support our
economy and help us to increase the production of
oil
|
M. O. C STARTED DRILLING
NOOR3 WELL
M.O. C.
started drilling Noor3 well. About this
subject, Mr. Sámi Naji the manager of fields
corporation tolled us we started the work in
5/10/2009 by helping of Iraqi drilling
company. We used the Rig oil well /22 . The
work will finish at a depth of 4202M to get
Nahir Omer reservoir. We will finish the
work within four months according to the
plan.
|
|