THE CORPORATION OF  FIELDS FINSHED

DRILLING  HALFAYA WELL/7                                          

 

      The corporation of fields finished drilling  Halfway well /7.About this subject Mr. Ali Jassim the  chief engineer , the supervisor on this project tolled us,we regarded this project as a large performance because we completed that project by  the notational efforts according to the plan. We finished working in a limited time. We could solve all the problems which faced the work. We finished drilling to a depth of  3765M after the penetration of the oil reservoir of Nahir Omer).

In addition , we could reduce the time  needed to complete the work.

We finished drilling fourth cave in 33 days. We reduced the cost  of this work for about 416500000 diners. We reduced the cost of chemicals and mud material for about 46000000 diners. We reduced the cost of fuel  for about34000000 diners.

.

This performance was done by the help of Mr. D .G .of M .O .C .and the manger of

 